Key Developments and Current Trends in Project Finance and Infrastructure

Hesketh Henry From the International Project Finance & Infrastructure Review 2026/27

Contributors

  • Simon Gray

    Partner

    Biography

    Simon Gray is a partner leading Hesketh Henry’s banking and finance practice and the firm’s Major Projects group. He has significant experience advising clients on the financing and development of complex, large-scale projects. He advises financial institutions, sponsors and investment funds across a variety of sectors, including social, economic and digital infrastructure (including PPPs), real estate developments and renewable energy, and supports clients across the full asset lifecycle from procurement and bankability through to delivery, operation and refinancing. Simon also has extensive experience in structured and acquisition financings and restructurings.

    Simon is named by Legal 500 for his work in Banking and Finance, and Best Lawyers for Project Finance and Development Practice and Banking and Finance Law. His clients say that he is “very good under pressure” and “his advice is informed, thorough and well thought out, and consistently of the highest standard.”

  • James Lewis

    Partner

    Biography

    James Lewis is a partner in Hesketh Henry’s construction and infrastructure practice and the firm’s Major Projects group. He has significant experience advising on structuring complex large-scale projects. He regularly advises a range of project participants on contractual documentation and provides legal and strategic advice at all stages of construction projects. He represents clients in all types of construction disputes including mediation, adjudication, arbitration and litigation. He works closely with principals, consultants and contractors across a wide range of sectors including infrastructure (including PPPs), energy, healthcare, education, hospitality and significant residential developments.

    James is admitted in New Zealand, Hong Kong and New York. He is recognised by clients as an expert in construction law, but also as being “down to earth”, able to “give practical and commercially focused advice” and provide “high levels of expertise, excellent client care, strong commerciality and focus on delivering for the client.”


A Market Open with Opportunity

New Zealand’s infrastructure market has entered a new phase and is open to private infrastructure capital.

The clearest signal came in July 2026, when two major public-private partnerships (PPPs) reached financial close: the first redevelopment phase of Christchurch Men’s Prison1https://www.beehive.govt.nz/release/christchurch-mens-prison-ppp-deal-signed and the Warkworth to Te Hana section of the Northland Corridor.2Warkworth to Te Hana PPP signed | Beehive.govt.nz The latter has a final project cost of NZ$3.649 billion on a net present value basis over a 32-year construction and operating period, making it the largest PPP in New Zealand’s history. Together, these transactions mark the return of large-scale availability-based procurement after an eight-year interval and reflect a broader policy position: that New Zealand’s significant long-term infrastructure needs cannot be met through public funding alone.

Both trace back to the 2025 New Zealand Infrastructure Investment Summit, convened to showcase the Government’s ambition and appetite to deliver infrastructure, and demonstrate a clear pipeline of opportunities3New Zealand Infrastructure Investment Summit 2025 – Outcomes Report – July 2025. The Christchurch Men’s Prison was a flagship announcement, and interest in the Northland Corridor produced three shortlisted consortia. Sixteen months later, both had closed.

The legal and regulatory environment has changed concurrently. New Zealand now has a permanent fast-track consenting regime4Fast-track Approvals Act 2024; Fast-track Approvals Act | Ministry for the Environment; Fast-track, new planning legislation replacing the Resource Management Act 1991, a reformed overseas investment approval process5Overseas Investment Act 2005; Reform of the Overseas Investment Act | Toitū Te Whenua – Land Information New Zealand;, a refreshed PPP framework supported by updated Treasury guidance6PPP guidance updated to support infrastructure | Beehive.govt.nz,7Guidance: New Zealand PPP Framework: A Blueprint for Future Transactions – November 2024 – Government of New Zealand, an expanded infrastructure levy regime8Infrastructure Funding and Financing Amendment Act 2026 | New Zealand Legislation; Infrastructure Funding and Financing Act 2020 – Ministry for Cities, Environment, Regions and Transport (Formerly Te Tūāpapa Kura Kāinga – Ministry of Housing and Urban Development), and a politically independent National Infrastructure Plan9national-infrastructure-plan-03032026.pdf. Taken together, these reforms make the market more predictable, more investable and more accessible to international capital.

This reform cycle has been designed, legislated and then tested through completed transactions inside a single parliamentary term. Procurement processes, standard-form documentation and risk allocation are modelled closely on Australian and United Kingdom practice, so the cost of entry diligence is unusually low for anyone active in either market. The pipeline is published, the approval pathways are defined, and when added to New Zealand’s political stability, strong institutions, transparent common law system, absence of exchange controls and established project finance market, the case for looking closely at New Zealand as a destination for investment is stronger than it has been for a decade.

Infrastructure is a National Priority

A notable feature of the current market is the emergence of political consensus around long-term infrastructure investment.

In February 2026 the Infrastructure Commission released New Zealand’s first independently produced National Infrastructure Plan10national-infrastructure-plan-03032026.pdf. The Government’s formal response, published in June 2026, fully supported 13 of the Plan’s 16 recommendations and supported the remaining three in principle11Government Response to the National Infrastructure Plan 2026 – June 2026. The response also carries contributions from the two largest opposition parties. The Labour Party’s response records its commitment to honouring what is contracted, underway and already funded (the proposed LNG terminal excepted). The Green Party supports all 16 recommendations while dissenting only on specific measures. In a sector historically exposed to electoral cycles, that alignment gives greater confidence that strategic priorities will survive a change of government. This is particularly relevant in an election year: New Zealand goes to the polls on 7 November 2026.

The Plan outlines that the cost of addressing New Zealand’s infrastructure deficit outstrips its ability to pay for it12national-infrastructure-plan-03032026.pdf. It recommends stronger governance, planning discipline, and project selection, and the Government has accepted that direction with a new assurance process for central government infrastructure investment due to be in place from 1 November 202613Government Response to the National Infrastructure Plan 2026 – June 2026.

The scale is substantial. As of June 2026, the National Infrastructure Pipeline recorded approximately NZ$290 billion of planned activity across almost 12,500 initiatives reported by 135 contributing organisations, of which NZ$71.2 billion was under construction and NZ$95.8 billion was fully funded11. Around NZ$17.5 billion of work is expected to enter construction in the twelve months from 1 July 2026, 89 per cent of it funded or with a confirmed funding source. That visibility is unprecedented in this market and allows early identification of opportunities.

A Front Door for International Capital

New Zealand has deliberately built an institutional front door. The Treasury leads advice on the funding and financing of infrastructure, including PPP policy; the Infrastructure Commission is the independent adviser responsible for the Plan and the Pipeline; Crown Infrastructure Delivery leads the safe, efficient and cost-effective delivery of quality infrastructure projects for Crown organisations; and National Infrastructure Funding and Financing Limited (NIFFCo), established in December 2024 by repurposing Crown Infrastructure Partners, is the Government’s investor shopfront and centre of expertise on infrastructure funding and financing14Infrastructure agencies | The Treasury New Zealand,15https://www.treasury.govt.nz/sites/default/files/2024-11/treasury-circular-2024-18.pdf.

NIFFCo’s mandate is the one directly relevant to overseas participants: it provides PPP and capital markets expertise to procuring agencies, supports business cases for projects that may use private finance, connects overseas investors and lenders into the Pipeline, and receives and evaluates market-led proposals on behalf of the Crown. For a sponsor with a proposition not yet in the Pipeline, the market-led proposal pathway remains the least-used route into this market, and one of the most interesting. Invest New Zealand plays a complementary role in promoting inbound investment.

PPPs have returned

The most important development in New Zealand project finance is the return of PPP procurement. Eight PPPs achieved financial close between 2012 and 2018: three correctional facilities, two roads of national significance and three bundles of schools6. The transactions that closed in July are the first new transactions in eight years.

New Zealand PPP project agreements are performance-based, placing private capital at risk if performance falls below agreed standards. The private partner designs, builds, finances and maintains (and may operate) the asset, and the public authority pays a unitary charge following service commencement. All transactions to date have been availability PPPs, meaning investors take Crown payment risk, and guidance indicates that the focus on availability and performance risk, rather than revenue risk, will continue16Public Private Partnerships (PPPs): Introduction to the New Zealand PPP Model and Policy – December 2025 – The Treasury. This produces the long-duration contracted revenue certainty and risk profile sought globally.

Lessons from existing New Zealand projects and from other jurisdictions have led to reform of the framework itself. The Treasury’s November 2024 blueprint for future transactions set out a series of improvements7. Updated guidance followed, covering bid cost reimbursement, price validation, split and staged completion, expansions and augmentations, Crown capability, and Crown capital contributions6. The framework applies a principle familiar to infrastructure investors everywhere: risk should sit with the party best able to manage or mitigate it at the least cost. Procuring agencies are also expected to take on board market feedback on risk allocation7.

The Warkworth to Te Hana procurement demonstrates those settings in operation: a more sophisticated approach to risk allocation, property and resource consents secured earlier, a stronger evidence base for affordability thresholds, bid cost reimbursement, price evaluation at the request for proposal stage and an optimisation phase between final bidders2. The Northway consortium, comprising Acciona Concesiones SL, Aberdeen Investments, Global Sustainable Infrastructure GP IV Ltd and Acciona Construction New Zealand Ltd, will design, build, finance, maintain and operate 26 kilometres of four-lane expressway under an agreement expiring in 2058, with unitary charge payments across a 25-year operating term. The final cost sits approximately NZ$251 million below the approved public-sector comparator, and will be financed through sponsor equity, senior bank debt and a Crown capital contribution (itself funded by a NZ$1.6 billion loan to the Transport Agency) to reduce the private debt requirement2.

The Christchurch Men’s Prison transaction is smaller but structurally similar. Southern Renewal Partners, led by Plenary with contractors Webuild and Leighs Construction, and facilities maintenance provider Serco, will design, construct, finance and maintain a NZ$440 million first phase comprising a 240-bed high-security unit, a 52-bed intervention and support building and a new health centre, with construction due to complete in late 20291. The maintenance term is 25 years and Corrections retains custodial operations. The programme is expressly multi-phased, with later phases to be assessed against capacity and funding.

Energy Transition and Renewable Infrastructure

Renewable energy is likely to remain one of New Zealand’s most important investment themes. The electricity system is already among the world’s most renewable: generation reached a quarterly record 96.4 per cent renewable in the December 2025 quarter17New Zealand Energy Quarterly Summary – December 2025. Several grid-scale projects have recently achieved fast-track approval, financial close or commissioning, including Contact Energy’s 380MW Southland wind farm, which would be the country’s largest18Fast-track approved project could deliver New Zealand’s largest wind farm | Beehive.govt.nz. Nonetheless, substantial further investment is required to meet electrification objectives and rising demand from transport, industry and digital infrastructure. This is reinforced by the Government’s goal to double renewable energy production by 205019Renewable energy investment opportunities in New Zealand | Invest New Zealand. Transmission constraints and grid connection capacity are becoming increasingly important to project development and financing.

The principal legal development is the Offshore Renewable Energy Act 2026, which came into force in July 202620Offshore Renewable Energy Act 2026; Building the future of offshore renewable energy | Beehive.govt.nz, with implementing regulations following in August 202621Offshore Renewable Energy Regulations 2026 | New Zealand Legislation. It establishes New Zealand’s first dedicated framework for offshore renewable generation through a staged process of feasibility permits, commercial permits and environmental approvals. Feasibility permits run for seven years, carry milestone requirements and are revocable if those milestones are not met. A commercial permit is required before construction, and decommissioning obligations must be backed by financial security. The regime is deliberately aligned with Australia’s offshore electricity infrastructure framework, lowering the regulatory learning cost for Australian developers and supply chains considering New Zealand. The first feasibility permit round is the event for developers to watch.

The commercial challenge across all renewable projects remains revenue certainty: projects will need to be supported by merchant exposure, corporate power purchase agreements or other commercial arrangements. That may prove more achievable than previously assumed for reasons discussed below.

Planning Reform

The transformation of the consenting framework is perhaps the most important legal reform from an investor perspective. Approvals for major infrastructure have historically been lengthy and uncertain, involving multiple statutory regimes, overlapping decision-makers and extensive litigation opportunities.

The Fast-track Approvals Act 2024 establishes a permanent regime to address that4. It consolidates resource consent and a wide range of other approvals into one application and one decision-making pathway. Expert panels determine applications rather than broader public processes, with challenges generally limited to questions of law and to a short statutory window. The effect is a substantial reduction in timing uncertainty and litigation risk.

By 28 September 2026 approvals had been granted for 35 projects under this regime, including roads of national significance, major port extensions, solar and wind farms, hydro-electric schemes and a new courthouse project22Fast-track approval for 250 new homes in Wānaka | Beehive.govt.nz. Decisions on substantive applications have taken an average of 118 working days from the point at which an application is confirmed complete and in scope. For investors accustomed to carrying prolonged consenting risk, this may ultimately prove as significant as any other reform.

The Resource Management Act 1991 is also being replaced. The Planning Act 202623Planning Act 2026 and the Natural Environment Act 202624Natural Environment Act 2026 received Royal assent on 30 September 202625New planning laws receive Royal assent | Beehive.govt.nz and are now in force. The Acts’ goals include enabling the use and development of land, the provision of infrastructure to meet current and future demand, and enabling the use and development of natural resources. Councils will continue to process consents under the existing regime during the transition. Transitional consenting arrangements take effect one month after Royal assent, and the new system is expected to become fully operational through 2029 and 203023. Projects already approved under fast-track are comparatively well insulated from that transition.

Water Infrastructure and Alternative Funding Models

Water infrastructure is emerging as one of the largest sources of future investment. Following the Local Government (Water Services) Act 2025, territorial authorities have adopted new delivery structures and must maintain water services delivery plans supported by long-term investment programmes26Local Government (Water Services) Act 2025. Its objectives include addressing substantial infrastructure deficits while creating economically regulated organisations capable of sustaining greater investment and borrowing capacity. Water is the second-largest sector in the Pipeline, at approximately NZ$5 billion, or 21 per cent of projected infrastructure spend in 202627tw-pipeline-snapshot-may2026-25th-may.pdf; tw-pipeline-snapshot-june2026-final.pdf.

The sector is also benefiting from more sophisticated financing mechanisms. The Infrastructure Funding and Financing Act 2020 allows infrastructure to be financed through special purpose vehicles supported by statutory levies on benefiting property owners, rather than through council balance sheets28https://www.legislation.govt.nz/act/public/2020/47/en/latest/#LMS235094. It has recently been amended to allow water organisations to impose levies, to streamline the levy order process, and to create an accelerated recovery mechanism8. This is expected to be an increasingly important source of off-balance-sheet funding and demonstrates a willingness to pursue alternative models where traditional public funding is insufficient. The Te Awa Lakes residential and commercial development in Hamilton is the latest example showing how levy-supported arrangements can enable transport and water infrastructure29https://teawainfrastructurelevy.co.nz/about-us/.

Foreign Investment and International Capital

New Zealand has traditionally balanced openness to foreign investment against sensitivity around land ownership and strategic assets. The pendulum is moving towards the former.

Changes to the Overseas Investment Act 2005 took effect in March 2026 to acknowledge the role of overseas investment in increasing economic opportunity5. The reforms consolidate the previous tests into a single national interest test applied through a three-stage, risk-based triage that targets screening towards more sensitive transactions. Existing pathways for farmland, fishing quotas and residential land remain alongside three new ones: a primary pathway for significant business assets and sensitive land, a production forestry pathway, and a pathway for qualifying investor visa holders acquiring housing above NZ$5 million.

The statutory timeframe for the new pathways is 15 working days, with most applications expected to be assessed within five working days30https://www.linz.govt.nz/sites/default/files/doc/MDL%20March%202026.pdf. Only the responsible Minister may decline consent. For sponsors evaluating New Zealand opportunities, that removes a source of execution risk historically difficult to price.

Digital Infrastructure and New Sources of Demand

Digital infrastructure has become one of the fastest-growing segments of the market. Microsoft, Google Cloud and Amazon Web Services have all launched local regions, and with New Zealand’s natural cooling advantages, abundant renewables, available land and highly skilled workforce, private investment continues to flow into data centres, AI services, submarine cable infrastructure and associated power and connectivity assets31Data and AI Infrastructure investment opportunities in New Zealand | Invest New Zealand.

Most of this has been funded using corporate balance sheets rather than project finance. That said, hyperscale demand is strengthening the economics of renewable generation and expanding the market for long-term corporate power purchase agreements, the revenue mechanism on which New Zealand’s renewable projects depend. The current Energy Minister has said that, in principle, data centres should underwrite new generation32AI data centres should underwrite new power generation – minister. Datagrid’s proposed Southland project has attracted

investment from Mercury NZ, one of the country’s largest gentailers, and the partnership between CDC Data Centres and Contact Energy underlines the importance of long-term supply arrangements to large-scale facilities. Where those relationships carry sufficient term and counterparty credit, conventional project debt will follow.

Outlook

New Zealand’s infrastructure market is better positioned than at any point in the last decade, and the steps taken by the current Government have collectively improved the investment environment. Opportunities are emerging across transport, renewable energy, water, social and digital infrastructure. Health, justice and education may provide the next wave of partnership and alternative financing transactions.

Challenges remain. Construction capacity is limited and workforce demand is a live constraint on delivery, cost pressures persist, and political transitions can alter procurement priorities. New Zealand is also a small market, and transaction volume will never match larger jurisdictions.

Yet the direction of travel is unmistakable. Successive reforms have engaged private capital, standardised procurement and allocated risk in a manner familiar to international investors, and two major transactions have now closed on those terms. For those seeking opportunities in developed markets, New Zealand offers a transparent framework for long-term investment, a published pipeline against which to plan, and a clear route through which to engage. This market now warrants active attention, and those who engage during this cycle will be best placed for the one that follows.

This article is written as at 30 September 2026.